Wondering what does an architect do once you hire one? In short, an architect turns your idea into drawings and specifications, then helps you check the building is built to them. Here is the path, stage by stage.
If you are new to the field, start with our architecture basics overview, then come back for the stage-by-stage view.
| Item | Value |
|---|---|
| Phases in the AIA B101-2017 owner-architect agreement | 5 phases |
| Schematic design, share of fee (rule of thumb) | 10% of fee |
| Design development, share of fee (rule of thumb) | 25% of fee |
| Construction documents, share of fee (rule of thumb) | 40% of fee |
| Construction administration, share of fee (rule of thumb) | 20% of fee |
| Construction phase, modeled duration | 24 months |
These figures come from Monograph’s guide to design phases, last updated June 11, 2024. They are rules of thumb and one modeled example, and they can change, so check the source before you rely on them.
Pre-design: working out what you need
Before any drawing, an architect helps define the program, the list of functions the building must serve. In the AIA’s best-practice article dated November 30, 2023, the program should include the estimated square footage of each usage type and any other elements that achieve the project goals. Read the AIA article for the full wording.
Programming is not always part of the basic package. In the AIA B101-2017 agreement, as Monograph describes it (last updated June 11, 2024), programming sits in the Supplemental Services table. You get it from your architect only if that table assigns it, and it carries a separate fee, according to Monograph’s guide.
Mastt’s guide, posted April 25, 2025, says this early stage often includes the following:
- A site survey
- A zoning analysis
- Early conversations about space needs, timeline and budget
A key output is a design brief, a document that summarises your goals, requirements and constraints and guides later decisions, as Mastt’s design phases guide explains.
Schematic design and design development
Most owners build once, which is why the phases come with a sign-off at the end of each one, as Monograph’s guide points out. The same guide notes that an owner who approved a floor plan in schematic design argues less about it later, when the construction documents are drawn.
In schematic design, the architect consults with you to set project goals and requirements. They then develop study drawings that show spatial relationships, scale and form for you to review. This is also the research phase, when zoning requirements and jurisdictional restrictions are discovered and addressed, according to the AIA’s November 30, 2023 article.
That article lists typical outputs of this phase:
- A site plan, floor plans, sections and an elevation
- Computer images, renderings or models
- A cost estimate based on overall project volume
The architect requests your approval of the schematic documents before design development starts, and again before construction documents begin, as Monograph’s guide describes the B101 rhythm.
Design development takes the agreed scheme one step further. The AIA says it lays out mechanical, electrical, plumbing, structural and architectural details, with drawings that often specify materials and the location of windows and doors. The phase often ends with a formal presentation to, and approval by, you as owner (AIA article).
Your architect also coordinates engineers here. In the B101 basic services as Monograph describes them, structural engineering plus mechanical and electrical engineering are included, while anything else is a supplemental or additional service (Monograph).
Construction documents: the set a builder prices
In construction documents, the architect produces drawings with greater detail, typically including specifications for construction details and materials. The set should hold all the information a contractor needs to price and build the project, according to the AIA’s November 30, 2023 article.
These drawings and specifications also become part of the building contract, as AIA Nebraska’s guide explains. That is why this is the stage where vague wishes have to become exact choices.
The style and performance goals you set earlier land in these drawings as materials and details. To see how one design tradition shapes those choices, read about modernist architecture characteristics. For the environmental side, our guide to sustainable architecture principles covers ideas an architect may weave in.

Bidding and construction administration
During bidding, the architect prepares the bid documents that go out to contractors. You, with the architect’s help, evaluate the bids and select a winner, and the final step is awarding the contract with a formal letter of intent so construction can begin (AIA article). Monograph adds that the 2017 edition of the B101 agreement renamed this phase “Procurement”, though many firms still say bidding (Monograph).
You are the one who hires the builder. AIA Nebraska’s guide says the architect may be willing to make some recommendations, and can help prepare bidding documents, invitations to bid and instructions to bidders (AIA Nebraska).
Construction administration (CA), which the AIA article calls contract administration, is rendered at the owner’s discretion and outlined in the owner-architect construction agreement. It runs from the initial construction contract until the final certificate of payment is issued (AIA article). The architect’s core job is to help the contractor build the project as specified in the approved documents.
Depending on the agreement, CA can include these tasks, drawn from Monograph, Mastt and AIA Nebraska:
- Making site visits to observe construction
- Reviewing submittals and shop drawings and responding to RFIs (requests for information)
- Reviewing the contractor’s applications for payment and issuing payment certificates
- Handling change orders
- Inspecting at substantial and final completion
How fee and time spread across the stages
Monograph’s guide gives rule-of-thumb fee shares drawn from AIA best practices, plus a modeled schedule. Treat them as one example, not a quote for your project. Here they are in order, from Monograph’s design phases guide:
- Schematic design: 10% of fee, 2 months modeled
- Design development: 25% of fee, 4 months modeled
- Construction documents: 40% of fee, 6 months modeled
- Procurement (bidding or negotiation): 5% of fee, 2 months modeled
- Construction phase (CA): 20% of fee, 24 months modeled
Real projects vary widely. Bucknell University’s published ranges for capital projects over $1 million run 3-6 months for schematic design and 3-20 months for construction administration, per Monograph. Use past projects of the same type as your guide.
Mastt argues that this structure reduces risk, improves communication and helps the final building reflect the original vision, as its guide puts it.
Where the architect’s job ends and the contractor’s begins
AIA Nebraska’s guide describes the split this way: architects and engineers give an idea definition, and the contractor takes that definition and turns it into physical reality (AIA Nebraska).
On site, the architect can assist you in making sure the project is built according to the plans and specifications. The contractor stays solely responsible for construction methods, techniques, schedules and procedures, per the same guide.
For public work, AIA Nebraska’s guide describes qualifications-based selection of design firms, in these steps:
- The client announces the need and invites interested firms to submit qualifications and experience.
- The client reviews the submissions and picks a short list of three to five firms.
- The client holds personal interviews with those firms.
- The client ranks the firms and invites the top-ranked one to negotiate a formal agreement.
Private clients often choose differently, but the idea is the same: compare qualifications, then agree a clear scope before work begins. AIA Nebraska’s page has the full question-and-answer text.
Frequently asked questions
Does an architect build the building?
Show answer
No. The contractor physically builds it and is solely responsible for construction methods, techniques, schedules and procedures, while the architect can help you check the work follows the plans, as AIA Nebraska’s guide explains.
Is programming included in an architect’s basic services?
Show answer
Not necessarily. In the B101 agreement as Monograph describes it, programming sits in the Supplemental Services table and is provided only if that table assigns it to the architect, for a separate fee (Monograph).
Does an architect help choose the contractor?
Show answer
Yes, in a supporting role. The AIA article says you, with the help of the architect, evaluate the bids and select a winning bid, so the decision stays with you (AIA).
Does an architect visit the site during construction?
Show answer
They can. AIA Nebraska’s guide says the architect can make site visits to observe construction, review the contractor’s payment applications and keep you informed, and the AIA notes that these services depend on the owner-architect agreement (AIA Nebraska).